Perham High School Update June 9 2017

The steel structure at Perham High School is started.  With foundation walls, piers, and some of the masonry block already laid, Olaf Anderson’s steel crew has started placing columns on the West side of the building where math and science classes will be held.  We will continue working on steel in this area and slowly…

Fargo City Hall Update May 4 2017

The primary steel structure is being finished up at City Hall, making way for metal decking and the concrete topping.  Starting from the top down, 4th floor & 3rd floor have been poured with second floor following this week.  Exterior metal stud walls have begun to be framed, along with window openings and parapets.

Perham High School in Motion

Construction on the new Perham high school has commenced as of the beginning of April.  The new facility will be attached to the existing middle school and will house grades 9-12.  The site has already been prepped with utility work, so we will be pouring footings and foundation walls this week.  Stay tuned for more…

Fargo City Hall Update – Feb. 13 2017

City Hall has volume now with a fair amount of steel up on the North end of the building.  The Southern portion of the building is underway with concrete footings being poured, CMU being placed for the elevator/stair shafts and foundation walls being formed.  We will start precast and steel on the Southern end as…

Fargo City Hall Update – Oct. 27 2016

Fargo City Hall has begun taking form as the footings are being poured and the basement parking garage walls are starting to be formed. The underground parking is the first portion to be constructed. It will be approximately 40,000 SF and will have 87 parking stalls.

Degelman Industries Officially Up-and-Running

Degelman Industries is up-and-running in full force. There was a ribbon cutting ceremony the other week to show their doors are open to the public. Degelman Industries is located just outside of Hillsboro, ND along Interstate 29. They specialize in the design, production, and testing of agricultural and industrial equipment. This new facility was designed…

St. Gabriel’s Community Center Update From Above

St. Gabriel’s addition & remodel is a 142,000 SF addition onto the existing community center located in Bismarck, ND. The addition is 4 stories and has 39 parking spaces below the main floor. There are 97 units (33 designated for basic care and 64 for assisted living), gym space, chapel, office space and a coffee…

Awards News

The following is awards received by Olaf Anderson. Staff recently attended a Ceco Building Systems National Convention and received an award for being one of the Top Ten Builders of the 786 authorized Ceco Builders nationwide. A Ceco Builder since 1988, we are recognized each year with Cumulative Volume Awards. Here are three of our…